The Before-It-Ships Checklist
The questions I'd ask on every item that's built somewhere else and shipped to your job, before it gets built, so nothing goes into fabrication on a guess and no late item eats your calendar.
On a drawbridge job in Virginia, Land to Sand Site Services found steel off by three sixteenths of an inch while it was still in the fabrication shop. Trimble, the company that makes the scanners they used, says that catch saved them from rework and an eight month delay. The part you can copy is when they looked, not what they looked with.
Here's why it matters on your jobs. Every week a job stays open, it costs you money just to keep it open. Builders call that general conditions: your super, your project management, insurance, the trailer, dumpsters on site, rental equipment. On county work, or working for a bigger GC, you can also get hit with liquidated damages, a set amount for every day you finish late, written right into your contract.
The same mistake gets three very different bills:
List everything on the job that gets built somewhere else and shipped to you. Those are your long lead items. Long lead just means it takes weeks to make, so if it's wrong, you wait those weeks all over again. Whatever's make or break on that job, the stuff that hurts the most when it shows up wrong, goes right at the top.
Before any of it goes into fabrication, go measure what it's going to land on. Then check that against the plans. On the job that's called field verifying: checking what's really built, not what the drawing says should be there.
You don't need a laser scanner for most of that. A tape measure, a habit and a date on the schedule will get you most of the way.
Every long lead item gets a date to measure the field before fabrication, and its lead time goes right on the schedule. When you bid, put a dollar number on every week a late item can cost you, not just the materials.
A worked example
Not a real job, just the math. Say a late item puts your job eight months behind, the delay in the bridge story. Say your general conditions run five thousand dollars a week. Eight months is about thirty five weeks. Five thousand a week, times thirty five, is a hundred and seventy five thousand dollars, and nobody built a single thing with it. Run the same math with your own weekly number before you price a late item.
Tuition isn't free. Every one of these mistakes costs somebody money. Make it the cheap kind, on paper, before anything ships.
One block per item. Fill it in when you build the list, and don't release the item to fabrication until every line has an answer.
Job: ____________
Item: ____________
Built by: ____________
Make or break? yes / no
LEAD TIME
Weeks to make: ____________
On the schedule: yes / no
FIELD CHECK BEFORE FABRICATION
Lands on: slab / opening / anchor bolts / other ____________
Field measure date: ____________
Measured by: ____________
Matches the plans? yes / no
If no, sent to architect or engineer on: ____________
PRICE
Our cost per week of delay: ____________
In the bid: yes / no
Sources
Keep reading free with your library card
One email opens this checklist and all 21 resources in Paul's library. No account, no password.
On the job you're running now, list every item that gets built somewhere else and shipped to you, and put the one that hurts most if it shows up wrong at the top.
Saving works best in your phone's browser. A copy is also in your inbox.