A Steel Mistake Under a Quarter of an Inch Saved a Bridge Job 8 Months

Land to Sand Site Services caught a steel mistake under a quarter of an inch and saved a bridge job 8 months. Why your schedule is half your margin.

Paul Maloney
Founder & CEO of Maloney Construction, Skoper and Skoper Labs
November 16, 2026
Watch the video, or read the article below.
4:51
10 chapters
  1. 0:00 3/16 of an inch, an estimated 8 months saved
  2. 0:12 A drawbridge, steel built in Canada
  3. 0:23 Scanned in 3D, off by 3/16
  4. 0:59 Trimble’s award, Trimble’s scanners
  5. 1:16 It’s not the steel, it’s the schedule
  6. 1:40 The math on a job of your own
  7. 2:28 One mistake, three bills
  8. 3:01 Trimble’s four steps, mostly without a scanner
  9. 3:19 Three habits for a normal commercial job
  10. 4:37 What shows up wrong most on your jobs?

Land to Sand Site Services caught a steel mistake under a quarter of an inch, and it saved a bridge job 8 months. That estimate comes from Trimble, the company that makes the scanners, and on November 4 they gave Land to Sand an award for it.

A drawbridge, with the steel built in Canada

They’re out of Currituck, North Carolina. They were replacing a drawbridge in Virginia, and the steel for it was being built in a fabrication shop up in Canada. That’s just where the steel gets cut and welded before they truck it out to the job.

So they scanned both places in 3D, the bridge site and the steel in the shop. A laser measures every surface and builds an exact copy on the computer, and they compared all of it against the design. And during fabrication, they found it. Some of those steel pieces were off by three sixteenths of an inch, on a whole bridge.

Illustration from the video: a crane lowering steel onto the drawbridge supports, with a close-up of the three sixteenths of an inch gap
0:44 in the video Some of those steel pieces were off by three sixteenths of an inch, on a whole bridge.

So before anything got installed, the team adjusted the concrete supports the steel was going to sit on, so the two would meet the way they really were. The steel went in, and it fit. Trimble figures that catch saved them from rework and an 8 month delay.

Now picture it the other way. The steel shows up at the bridge, the crane’s ready, the crew’s ready, and it doesn’t fit. Everybody just stands there.

Trimble’s award, Trimble’s scanners

To be fair, this is Trimble’s award, and it went to a job done with Trimble’s own scanners. The scanner found it, no question. But the part you can copy is when they looked, not what they looked with.

And you don’t have to build bridges for this. Your doors, your storefront glass, your trusses, they’re all built somewhere else too.

It’s not the steel, it’s the calendar

I’m a commercial GC in Florida, and when I read that story, I wasn’t thinking about the steel. I was thinking about the calendar, because if you’re losing money on a job, you’re usually not losing it on your work. You’re losing it on the calendar.

Here’s why. Every week a job stays open, it costs you money just to keep it open. Builders call that general conditions: your super, your project management, insurance, the trailer, dumpsters on site, rental equipment, you name it.

The math on a job of your own

Let’s do the math out loud on a job of your own. Not this bridge, just an example. Say your general conditions run 5,000 dollars a week. 8 months is about 35 weeks, so 5,000 a week, times 35. That’s 175,000 dollars, and nobody built a single thing with it.

Illustration from the video: the three sixteenths of an inch gap between the steel and its support, next to a tape measure and a fingertip
2:08 in the video So something smaller than your fingernail turns into six figures

And if it’s county work, or you’re working for a bigger GC, you can get hit with late penalties on top of that. They’re called liquidated damages, a set amount for every day you finish late, written right into your contract.

So something smaller than your fingernail turns into six figures, and it’s not the steel that’s expensive, it’s the calendar. Every one of those weeks comes straight out of what you keep.

Your schedule is half your margin.

I made a free one page checklist for the stuff that gets built somewhere else. It’s the questions I’d ask on every one before it gets built, so nothing goes into fabrication on a guess.

One mistake, three bills

That’s what it costs. Now, how do you actually catch it on your jobs?

Land to Sand found that steel mistake while the steel was still being built, before it ever went up on the bridge. That’s the cheapest time to catch a mistake on your jobs too. The way I see it, the same mistake gets three very different bills:

  • On paper, it’s an email and a revised drawing.
  • At the shop, it’s a re-⁠⁠cut and maybe a few days.
  • On site, it’s weeks of your super, your trailer and your rentals sitting there while somebody figures it out.

Trimble boiled what Land to Sand did down to four steps:

  1. Get a look at what’s really there early.
  2. Compare it to the design.
  3. Tell everybody what’s different.
  4. Fix it while it’s still small.

And honestly, you don’t need a laser scanner for most of that. A tape measure, a habit and a date on the schedule will get you most of the way.

Three things for a normal commercial job

Here’s my version of that, how I’d run it on a normal commercial job. Three things, and none of them need new software. We’re going to build a list, and whatever’s make or break on that job, the stuff that hurts the most when it shows up wrong, goes right at the top.

  1. List everything on the job that gets built somewhere else and shipped to you. Structural steel, trusses, storefront, doors and frames, cabinets, the curbs your rooftop units sit on, you name it. Those are your long lead items. Long lead just means it takes weeks to make, so if it’s wrong, you wait those weeks all over again.
  2. Before any of it goes into fabrication, go measure what it’s going to land on. The slab, the opening, the anchor bolts that are actually in the ground. Then check that against the plans. If they don’t match, it goes back to your architect or your engineer before anything gets built. They decide the fix, you just find it while it’s still on paper.
  3. Put it on the schedule and in the price. Every long lead item gets a date to measure the field before fabrication, and its lead time goes right on the schedule. When you bid, put a dollar number on every week a late item can cost you, not just the materials.

That’s it.

At the end of the day, every one of these mistakes costs somebody money, and I always say tuition isn’t free. Just make it the cheap kind, on paper, before anything ships.

My free checklist walks you through those three steps for every item on your list.

What’s the one thing on your jobs that’s built somewhere else and shows up wrong the most? Is it doors and frames, storefront, or trusses?

Questions people ask

How did a steel mistake save a bridge job 8 months?

They scanned the bridge site and the steel in the shop in 3D and compared all of it against the design. Some of those steel pieces were off by three sixteenths of an inch, so before anything got installed, the team adjusted the concrete supports the steel was going to sit on. Trimble figures that catch saved them from rework and an 8 month delay.

What are general conditions in construction?

Every week a job stays open, it costs you money just to keep it open. Builders call that general conditions: your super, your project management, insurance, the trailer, dumpsters on site, rental equipment.

What are liquidated damages?

Late penalties: a set amount for every day you finish late, written right into your contract.

What is a long lead item?

Everything on the job that gets built somewhere else and shipped to you. Long lead just means it takes weeks to make, so if it’s wrong, you wait those weeks all over again.

Do I need a laser scanner to catch fabrication mistakes?

You don’t need a laser scanner for most of that. A tape measure, a habit and a date on the schedule will get you most of the way.

What should I check before something goes into fabrication?

Go measure what it’s going to land on: the slab, the opening, the anchor bolts that are actually in the ground. Then check that against the plans. If they don’t match, it goes back to your architect or your engineer before anything gets built.

Sources

  1. Trimble: Trimble Announces Winners of 2026 Construction Innovation Awards (November 4, 2026)
  2. Graduate School USA: Understanding General Conditions in Construction Projects

Your next step

01

This checklist · free

The Before-⁠⁠⁠It-⁠⁠⁠Ships Checklist

The questions I’d ask on every item that’s built somewhere else and shipped to your job, before it gets built, so nothing goes into fabrication on a guess and no late item eats your calendar.

Your first moveOn the job you’re running now, list every item that gets built somewhere else and shipped to you, and put the one that hurts most if it shows up wrong at the top.

02

Paul’s Library · free

Get free access to Paul’s whole library

One email opens every checklist and template from Paul’s videos, right here on the site. New ones come by email as he adds them.

  • Sub Coverage Checklist
  • Desk Jobs Checklist
  • First Ten Questions Checklist
  • Backlog Worksheet
  • ChatGPT Page Claim Checklist
  • Before-It-Goes-Down Checklist
  • AI Meeting Checklist
  • Before-⁠⁠⁠It-⁠⁠⁠Ships Checklist
  • Claude Bank Account Checklist
  • Bid Pipeline Worksheet
  • Weekly Owner Report Template
  • Empty Seat Checklist
  • ChatGPT Short List Checklist
  • Vendor Number Checklist
  • Paper Job Worksheet
  • Take-⁠⁠⁠Back Checklist
  • AI Payback Worksheet
  • AI Agent Job Card
  • Rent-⁠⁠⁠or-⁠⁠⁠Own Agent Checklist
  • Automate-⁠⁠⁠Last Worksheet
  • AI Takeoff Checklist

03

Work with Paul

Work with Paul

Through Skoper Labs, I start where you spend the most time, then build AI tools around how your company actually works. You own them, and nothing gets bent around a platform that doesn’t fit.

Free, by email

Follow by email: Paul's new resources

An email when Paul adds a new resource to the library.

You confirm on Paul's Library.
Your email stays with Paul and the team that runs this library. Never sold.
Thanks
Share this article
Paul Maloney
Written by

Paul Maloney

Founder & CEO of Maloney Construction, Skoper and Skoper Labs

I'm a third-⁠⁠generation builder and the founder and CEO of Maloney Construction, a commercial general contractor in Florida. My estimator and I ran hundreds, then thousands, of estimates until a set of plans could go in and a full estimate come out in minutes. That became Skoper, which other contractors now pay for. Every resource here is built from my videos and fact-⁠⁠checked.

About Paul
Keep watching

More from Paul

All videos
Video thumbnail: Florida Says a Miami Company Paid $9,300 for Comp That Should Have Cost Almost $110,000. Not a Better Price, a Missing Cost
Nov 23

Florida Says a Miami Company Paid $9,300 for Comp That Should Have Cost Almost $110,000. Not a Better Price, a Missing Cost

Florida says a Miami construction company paid $9,300 for a year of workers' comp it should have paid almost $110,000 for. Here's what I'd check on a sub.

Video thumbnail: A 153-Year-Old Builder Just Bet $150 Million on Robots
Nov 22

A 153-⁠⁠⁠Year-⁠⁠⁠Old Builder Just Bet $150 Million on Robots

Taisei is putting $150 million into AI and robots. In my company, AI didn't show up on the job site. It showed up at my desk.

Video thumbnail: Anthropic's New Claude Scared Contractors. Most Are Asking It About Dinner
Nov 21

Anthropic’s New Claude Scared Contractors. Most Are Asking It About Dinner

Anthropic's new Claude read a set of construction drawings and built a 3D model of a house. Most contractors only ask it what to cook for dinner.